Wednesday, July 9, 2014

Construction for the Town of Sunol Fire Suppression Project is Starting

We are getting started on construction to improve the water distribution system and construct approximately 26 fire hydrants in the Town of Sunol. 

Please join us for a project groundbreaking on Friday, July 11, at 10:30 a.m. at the parking lot (intersection of Main Street, Kilkare Road, and Foothill Road) in Sunol, California.
We will enjoy light refreshments at the park afterwards.

Where is construction right now?
During the Weeks of July 7—July 21, 2014

Pipeline installation will occur at:
  • Sunol Glen School
  • Main Street up to the Railroad Crossing
  • Bond Street
In August, we plan:
  • Pipeline Installation on East Foothill Road to  the Kilkare Road intersection
  • Jack and Bore crossing underneath Alameda County Railway at the intersection of Main Street, Kilkare Road, and Foothill Road.
o   We will cross under the railroads using a jack and bore method. The contractor will dig two large pits on each side of the crossing, insert pipeline casing into the pits and move the pipe beneath the railroad crossings. Each jack and bore crossing will take approximately 30 days.

What to Expect during Construction:
  • One-lane traffic through construction zones during work hours. This will cause some delays, so please plan ahead.
  • Possible Work Hours: 7:00 a.m. to 5:00 p.m.
  • Weekend work might be necessary, but we will provide advanced notice.
  • Night work will be necessary during pipeline/tank shutdowns. We will minimize noise.  Some residents will have nighttime water outages with advance notice.
  • Access to private driveways and around streets will be available at all times.


Stay in touch
Visit us  online here

Call us 24/7 at (866) 973-1476.
blauppe@sfwater.org
epowell@sfwater.org

See you around the Sunol Valley!

Friday, June 20, 2014

The WSIP Turns 10!


This year the Water System Improvement Program (WSIP) turns 10! One of the largest infrastructure projects in the nation, the WSIP is repairing, replacing and upgrading our aging water infrastructure to ensure we can deliver water to customers following an earthquake. We’ve gotten a little nostalgic about how far we’ve come in the last 10 years, and we would like to share this video with you.



Now 80 percent complete, the WSIP has already provided increased reliability to the water supply for customers as a result of the completion of some of the program’s major projects. The program has created over 6 million construction craft hours to date, employing more than 11,000 workers since 2007. Nearly half of those workers live in our four-county service area.

An Ode to the Calaveras Spillways, old and new

Workers repair original Calaveras Dam spillway in 1939


What is a spillway?
A spillway is an important safety feature on a dam that impounds water behind it to prevent the dam from overtopping and suffering damage during a flood. The spillway is often an open chute or channel that allows water when it reaches a high level in the reservoir to safely bypass the dam and flow downstream without causing any damage to the dam.

History of the Calaveras Dam Spillway

The original spillway on Calaveras Dam was completed in 1925. In 1939, workers had to repair the original spillway after damage was caused by a flood occurred in the Winter of 1937-1938.

Spillway Work Today

Back in March work began on the new spillway. We have made much progress since then to construct the spillway, which will be 1550 feet long. Approximately 40,000 cubic yards of concrete, equivalent to one football field filled six feet deep, is being used to build the structure. All of the concrete is being supplied by our on-site concrete batch plant.
Because of its crucial function in dam safety, it’s important to make sure that the spillway structure stays intact during an earthquake on the nearby Calaveras Fault. So we are drilling anchors, a solid steel rod, about 25 feet into the rock around the spillway to provide support and prevent damage to the structure during any seismic activity.  We are installing 1,825 anchors, that’s a lot of anchors!  The spillway is expected to be completed in mid-2015.



View of the left wall of the new Calaveras Dam spillway. The purple anchor in the foreground will be encased in the concrete slab (foundation) being formed here. The exposed ends of the wall anchors will be encased in a block of concrete as part of the spillway wall.


Aerial view of new spillway taking shape at the left abutment.
Red arrows indicate the top of the spillway.



Tuesday, June 10, 2014

Neighbors Catch up on the New Irvington Tunnel

Thank you to all of the community members who dropped by the New Irvington Tunnel Open House at the Mission Coffee House last week!  It was really great to see you.  For those of you who weren’t able to attend, here are the highlights as shared by the project team.
  • The New Irvington Tunnel Project is currently 95% complete.
  • The steel liner of the tunnel has been installed. We are welding and grouting the space between the tunnel lining and the outside of the tunnel to seal the tunnel off from groundwater intrusion.
  • The 3.5 mile New Irvington Tunnel will be brought into service sometime this fall 2014, allowing us to take the old tunnel out of service for inspection and possible repairs.
  •  Overall project completion is anticipated in fall 2015, soon after we complete site restoration of all of the above ground work.
  • The New Irvington Tunnel runs parallel to the existing tunnel (which was built in 1932)  between the Sunol Valley south of Highway I-680 and Fremont, California. It provides a seismically designed connection between Sierra Nevada and Alameda Watershed water supplies and 2.6 million Bay Area customers.
We will be back out with another open house in a about three months, so we hope you can make the next one. 
Neighbors have some tunnel talk at the New Irvington Tunnel Open House

Thursday, May 29, 2014

New Irvington Tunnel Project Open House on June 3rd

Construction on the New Irvington Tunnel is nearing completion! We anticipate commissioning the new tunnel sometime this Fall 2014. The new tunnel will provide a seismically-designed connection between water supplies from the Sierra Nevada Mountains and the Alameda Watershed, providing water to our 2.6 million customers. Work still lies ahead, with project completion expected in mid-2015. 

Join us on June 3, 2014 from 4:30 pm to 6:30 pm at Mission Coffee House (151 Washington Blvd., Fremont CA). The project team will be present to answer any of your questions and discuss what to expect post-construction for our Groundwater Management Plan participants. 

View from inside a section of the New Irvington Tunnel

Tuesday, May 27, 2014

Alameda County Residents Contribute to 10 Years of WSIP Success

It seems like only yesterday the San Francisco Public Utilities Commission launched the Water System Improvement Program (WSIP). However, April marked the 10-year anniversary of WSIP, and, perhaps it seems like time has flown by since we’ve been busy at work!!  Since the start, 11,000 workers have been employed by the program.

Nearly six million craft hours have been completed on the program to date, which includes 725,000 apprenticeship hours.  Plus, San Francisco and service-area residents have worked 50 percent of those craft hours. In fact, Alameda County residents are responsible for the largest percentage of total hours worked on WSIP out of all the participating counties!

Thanks in part to the hard work of Alameda County residents, the WSIP is now 80 percent complete. The WSIP will ensure the Hetch Hetchy Regional Water System, which serves 2.6 million customers in the Bay Area, will be able to withstand a major earthquake or drought and continue to deliver water to customers.

                       A crew member upgrades the San Antonio Pump Station, a key WSIP project now complete.

Thursday, May 8, 2014

Sunol Glen School Students Celebrate Earth Week with Us!

What do ancient shark teeth, wasps nests, and owl pellets have in common? All were on display last week at the Sunol Glen School’s Earth Day Science celebration last week.  We were lucky enough to have been invited to participate, along with other local groups and leaders.  The kids, grades Kindergarten through eighth grade, learned about the importance of building a seismically upgraded replacement dam at the Calaveras Reservoir. Our project Geologist Bradley Erskine showed some fascinating fossils found at the Calaveras site during construction. The biggest hit with the students by far was a prehistoric shark tooth possibly from a Megladon, dating at approximately 20 million years old.  We had a great time answering questions about how water gets to your tap and the importance of the Water System Improvement Program to future generations.

Having met the leaders of tomorrow at Sunol Glen School, we know the future is in good hands! Sunol Glen Schools students proved themselves to be inquisitive and curious scientists at Earth Day on May 2nd. 

Geologist Bradley Erskine and Natural Resources staffer Amy Dawson share fossil finds from Calaveras Dam to the Sunol Glen School students

Sample fossils of prehistoric shark teeth dating over 20 million years old