We are
getting started on construction to improve the water distribution system and
construct approximately 26 fire hydrants in the Town of Sunol.
Please
join us for a project groundbreaking on Friday, July 11, at 10:30 a.m. at the
parking lot (intersection of Main Street, Kilkare Road, and Foothill Road) in
Sunol, California.
We will enjoy light refreshments at the park afterwards.
We will enjoy light refreshments at the park afterwards.
Where is
construction right now?
During
the Weeks of July 7—July 21, 2014
Pipeline
installation will occur at:
- Sunol
Glen School
- Main
Street up to the Railroad Crossing
- Bond
Street
In
August, we plan:
- Pipeline
Installation on East Foothill Road to the Kilkare Road intersection
- Jack
and Bore crossing underneath Alameda County Railway at the intersection of
Main Street, Kilkare Road, and Foothill Road.
o We will
cross under the railroads using a jack and bore method. The contractor will dig
two large pits on each side of the crossing, insert pipeline casing into the
pits and move the pipe beneath the railroad crossings. Each jack and bore
crossing will take approximately 30 days.
What to
Expect during Construction:
- One-lane
traffic through construction zones during work hours. This will cause some
delays, so please plan ahead.
- Possible
Work Hours: 7:00 a.m. to 5:00 p.m.
- Weekend
work might be necessary, but we will provide advanced notice.
- Night
work will be necessary during pipeline/tank shutdowns. We will minimize
noise. Some residents will have nighttime water outages with advance
notice.
- Access to private driveways and around streets will be available at all times.
Stay
in touch
Visit
us online here
See
you around the Sunol Valley!

No comments:
Post a Comment