Friday, April 3, 2015

Town of Sunol Fire Suppression Project: Slurry Seal of Main Street to Begin April 6, 2015


Week of April 6, 2015  and end the Week of April 24, 2015

7:00 a.m. to 6:00 p.m. Monday - Friday

As promised, we will install a new slurry seal on Main Street, between Bond and Kilkare Road. This work is scheduled to begin during the week of April 6. It will take approximately three weeks to complete this work.

What to Expect:

·         Work hours are 7 a.m. to 6 p.m. - Monday - Friday

·         There will be no parking on Main Street during these times – to prepare the road, slurry seal, and allow the seal to properly cure before traffic can safely drive on it again.

·         To avoid potential damage to your car from our operations, as well as potential towing a car left on Main Street, please obey the no parking signs.

·         One lane of Main Street will remain open to traffic, but please allow extra time to pass through the area.

·         The equipment and trucks related to this work will generate noise and dust.

 
Sequence of work:

o   Crews will grind down the existing street striping to prepare the road for its new slurry seal. This will take an estimated one-two days for each side of the street starting on Monday, April 6, 2015.

o   Slurry Seal Main Street Lane 1 (West Lane – on the Bosco’s and Railroad Café side of the street)

§  When the street is prepared for the slurry seal, crews will begin work on the West lane (Rail Road Café side) of Main Street.

§  Crews will slurry seal that side of the street starting at Kilkare Road and finish near Sunol Glen School at the end of the day.

o   Slurry seal lane 2 (East Lane – on the same side of the street as the Post Office)

§  Crews will start at the south side of Main Street and move back towards the Kilkare Road intersection on the eastern lane of traffic. 

§  Crews will be sure that cars can exit and enter the school for pick up and drop off times. 

o   Once the new slurry seal has properly dried, new street striping will be installed.

o   Curing should take a week or so.

We will work with the school and businesses located on Main Street to minimize any impacts because of this work.

Thank you for your patience!
As always, please do not hesitate to contact us with any questions, comments, or concerns.
24-hour Answering Line: (866) 973-1476

blauppe@sfwater.org

 

 

 

Monday, November 24, 2014

Update on the Town of Sunol Fire Suppression Project for the weeks of November 24 and December 1, 2014

The majority of the work within the Town has been completed. However, there is some work left to be done.

Construction Currently Underway or Planned for the Next 2 weeks

Pipeline connections at Sunol Glen School

Pipeline connections will be made between the new and old systems at the Sunol Glen School Parking lot the week of December 1st.  We will minimize any impacts to the school. The water supply to the town and school will not be affected. 

Service Connection Upgrades

As part of this project, SFPUC crews, together with our contractor, will inspect selected service connections of SFPUC customers. The service connection consists of the section of pipe between the water meter box and the street main which is maintained by the SFPUC. Should the inspection show the connection needing an upgrade, we will schedule a replacement and notify the property owner.

The connections on Main Street will be first, with inspections starting the week of Thanksgiving. 

Installation of bollards around fire hydrants

In order to protect some of the newly installed hydrants from accidental damage from vehicles, we will install bollards around the more exposed hydrants after the week of December 8th.  These bollards will conform with Alameda County Fire Specifications.

Installation of one of the two replacement tanks on tank hill continues. Work on the tanks on the hill will continue through next summer.

Pavement Restoration 

Once all the construction work within town is complete, we will work with Alameda County inspectors, repair street structural damage caused by the construction, and slurry seal Main Street.



The Jack and Bore work to lay pipe underneath the Union Pacific Railroad on Main Street was
recently completed.


What has been completed to date:

  • Installation of approximately 2 miles of transmission mains on Main St, Bond St, Foothill East and West and Kilkare Road.
  • Placement of all of the 26 planned fire hydrants.
  • Placing pipe across three bridges: Bond, Foothill, and Kilkare
  • Removal of two water tanks on Tank Hill.
  • Pipeline tie in work at Kilkare Road
  • Jack and Bore Crossing of Alameda County Railroad at the intersection of Main Street, Kilkare Road, and West Foothill Road.
  • Jack and Bore crossing under the Union Pacific Railroad on Main Street.
  • Pipeline Tie in work on Main Street near Bond


What is coming:

  • The new hydrants will be charged and ready for use.
  • The new water storage tank on Tank Hill will be placed in service during the next 3 months.
  • Thereafter, a pair of older water storage tanks will be demolished
  • and construction will start on the second water storage tank.


As always, please do not hesitate to contact us with any questions, comments, or concerns.

24-hour Answering Line: 
(866) 973-1476

epowell@sfwater.org
blauppe@sfwater.org

Thank you for your patience!

Friday, October 3, 2014

Town of Sunol Fire Suppression System Project

Construction Update

Railroad Crossings:
On Monday, October 6, 2014 crews will start the jack and bore work to cross under the Alameda County Rail Road at the intersection of Main Street, Kilkare Road, and West Foothill Road. If work proceeds as planned, the contractor will begin the jack and bore work underneath the Union Pacific Railroad on Main Street the week of October 20, 2014. This means construction at both railroad crossings will occur at the same time.

What to Expect:
* Crews will insert a steel casing from the driving pit at the intersection of West Foothill and Kilkare Road to a receiving pit (next to the Depot Parking lot).

* Kilkare Road will be reduced to one-lane traffic during daytime at the railroad crossing. We appreciate your patience with the expected traffic delays in the area.

* Access through the area will be allowed at all times, but please prepare for delays.

* Crews might need to hand drill under the railroads to remove rocks. The equipment will generate some noise.

Bridge Crossings:
Next week, crews will complete all work related to the bridge crossings at Sinbad Creek on Bond Street as well as on Foothill Road.

Hydrant Installation:
The majority of the hydrants will have been installed at their marked locations by the end of October. There is one hydrant on Main Street that will not be installed until after the jack and bore work is completed. The hydrants should be available for use in November.

As always, please do not hesitate to contact us with any questions, comments, or concerns. The 24-hour Answering Line: (866) 973-1476 or epowell@sfwater.org or blauppe@sfwater.org.

Thank you for your patience!

Friday, August 8, 2014

Town of Sunol Fire Suppression Project Update

Kilkare Road, here we come!

Construction has begun to improve the water distribution system and fire hydrants in the Town of Sunol. The project includes constructing two miles of new pipelines on County roads, installation of approximately 26 new fire hydrants, and replacing the existing water tanks that serve the Town of Sunol.

Here’s an update, hot off the presses as of August 8, 2014
  • What we’ve completed to date: Construction Crews have installed new pipeline on Main Street, Bond Street, Foothill Road West and East of Kilkare Road, and at Sunol Glen School. Hydrant locations have also been staked in these areas as well.
  • What’s next: Starting the week of August 11, 2014, our crews will next start pipeline installation on Kilkare Road, starting at the intersection with Foothill Road, and moving all the way up to the ‘600 block’ of Kilkare Road. Pipeline installation on Kilkare should be completed by Labor Day.
  • Hydrant Installation: Hydrants will be installed at marked locations   during this time period as the contractor’s schedule allows. 


What will come after that? Construction Look-ahead for September 2014:
  • Jack and Bore Crossing underneath Alameda County Railway at the intersection of Main Street, Kilkare Road, and Foothill Road.
  • Jack and Bore Crossing underneath Union Pacific Railroad on Main Street is scheduled to start at the end of September.


What to Expect during Construction:
- One-lane traffic through construction zones during work hours. This will  cause some delays, so please plan ahead.
- Work Hours: 7:00 a.m. to 5:00 p.m.
- Limited Work on Saturdays for a small crew to install hydrants.
- Night work will be necessary during pipeline/tank shutdowns. We will minimize noise. 
- Access to private driveways and around streets will be available at all times.



Stay in Touch:
24-hour Answering Line:
(866) 973-1476

Visit our blog sfwater.org/sunolvalley
Thank you so much for your patience and kind consideration during construction!

Wednesday, July 9, 2014

Construction for the Town of Sunol Fire Suppression Project is Starting

We are getting started on construction to improve the water distribution system and construct approximately 26 fire hydrants in the Town of Sunol. 

Please join us for a project groundbreaking on Friday, July 11, at 10:30 a.m. at the parking lot (intersection of Main Street, Kilkare Road, and Foothill Road) in Sunol, California.
We will enjoy light refreshments at the park afterwards.

Where is construction right now?
During the Weeks of July 7—July 21, 2014

Pipeline installation will occur at:
  • Sunol Glen School
  • Main Street up to the Railroad Crossing
  • Bond Street
In August, we plan:
  • Pipeline Installation on East Foothill Road to  the Kilkare Road intersection
  • Jack and Bore crossing underneath Alameda County Railway at the intersection of Main Street, Kilkare Road, and Foothill Road.
o   We will cross under the railroads using a jack and bore method. The contractor will dig two large pits on each side of the crossing, insert pipeline casing into the pits and move the pipe beneath the railroad crossings. Each jack and bore crossing will take approximately 30 days.

What to Expect during Construction:
  • One-lane traffic through construction zones during work hours. This will cause some delays, so please plan ahead.
  • Possible Work Hours: 7:00 a.m. to 5:00 p.m.
  • Weekend work might be necessary, but we will provide advanced notice.
  • Night work will be necessary during pipeline/tank shutdowns. We will minimize noise.  Some residents will have nighttime water outages with advance notice.
  • Access to private driveways and around streets will be available at all times.


Stay in touch
Visit us  online here

Call us 24/7 at (866) 973-1476.