Weather in the Sunol Valley has been hot lately, and the fire danger is high. The Alameda Siphon #4 Project team is on high alert to avoid activities that might cause sparks in the dry grass areas.
Demolition continues on the hillside east of Calaveras Road in anticipation of the Coast Range Tunnel Shutdown this winter.
Tuesday, September 29, 2009
Thursday, September 10, 2009
Mobilization Continues
Construction crews installed trailers and are are putting up perimeter fencing this week. Preparations have begun for some demolition of existing facilities on the hillside on east side of Calaveras Road.
Wednesday, September 2, 2009
Welcome
Welcome to the Sunol Valley Water System Upgrades Blog!
Stay tuned for construction updates on the Alameda Siphon #4 Project soon.