Wednesday, April 8, 2015

Construction Advisory: Town of Sunol Fire Suppression Project

What to Expect:

Thursday, April 9, 2015
Slurry Seal Main Street Lane 1 (West Lane – on the Bosco’s and Sunol Railroad Café side of the street).

To Residences and businesses on Main Street on the Sunol Railroad Cafe of the Street:
  • Please remove your cars from your driveway before 7:00 a.m. Thursday if you need to exit during 7:00 a.m. to 6:00 p.m. Once the slurry seal is placed, it will take hours to cure, and you cannot drive over it.
  • Please remove your car from the street before 7:00 a.m. on Thursday if you regularly park on the street.
  • You will be able to access your driveways again  after 6:00 p.m. on Thursday.
  • Pedestrians will be able to cross  the slurry seal safely during the day.
Friday, April 10, 2015
Slurry seal Main Street  Lane 2 (East Lane – on the Post Office Side of the Street ) 
To residences on the Post Office Side of the Street:
  • Please remove your cars from your driveway before 7:00 a.m. Friday if you need to exit during 7:00 a.m. to 6:00 p.m. Once the slurry seal is placed, it will take hours to cure, and you cannot drive over it.
  • Please remove your car from the street before 7:00 a.m. on Friday if you regularly park on the street.
  • You will be able to access your driveways again  after 6:00 p.m. on Friday.
  • Pedestrians will be able to cross  the slurry seal safely during the day.
We will avoid pick up and drop off times at the school.
There will be one lane of traffic flowing through the Town at all times.

Thank you for your patience!
Questions? 24-hour Answering Line:  (866) 973-1476
epowell@sfwater.org
blauppe@sfwater.org
Visit our blog: sfwater.org/sunolvalley

Friday, April 3, 2015

Town of Sunol Fire Suppression Project: Slurry Seal of Main Street to Begin April 6, 2015


Week of April 6, 2015  and end the Week of April 24, 2015

7:00 a.m. to 6:00 p.m. Monday - Friday

As promised, we will install a new slurry seal on Main Street, between Bond and Kilkare Road. This work is scheduled to begin during the week of April 6. It will take approximately three weeks to complete this work.

What to Expect:

·         Work hours are 7 a.m. to 6 p.m. - Monday - Friday

·         There will be no parking on Main Street during these times – to prepare the road, slurry seal, and allow the seal to properly cure before traffic can safely drive on it again.

·         To avoid potential damage to your car from our operations, as well as potential towing a car left on Main Street, please obey the no parking signs.

·         One lane of Main Street will remain open to traffic, but please allow extra time to pass through the area.

·         The equipment and trucks related to this work will generate noise and dust.

 
Sequence of work:

o   Crews will grind down the existing street striping to prepare the road for its new slurry seal. This will take an estimated one-two days for each side of the street starting on Monday, April 6, 2015.

o   Slurry Seal Main Street Lane 1 (West Lane – on the Bosco’s and Railroad Café side of the street)

§  When the street is prepared for the slurry seal, crews will begin work on the West lane (Rail Road Café side) of Main Street.

§  Crews will slurry seal that side of the street starting at Kilkare Road and finish near Sunol Glen School at the end of the day.

o   Slurry seal lane 2 (East Lane – on the same side of the street as the Post Office)

§  Crews will start at the south side of Main Street and move back towards the Kilkare Road intersection on the eastern lane of traffic. 

§  Crews will be sure that cars can exit and enter the school for pick up and drop off times. 

o   Once the new slurry seal has properly dried, new street striping will be installed.

o   Curing should take a week or so.

We will work with the school and businesses located on Main Street to minimize any impacts because of this work.

Thank you for your patience!
As always, please do not hesitate to contact us with any questions, comments, or concerns.
24-hour Answering Line: (866) 973-1476

blauppe@sfwater.org

 

 

 

Monday, March 23, 2015

Scheduled Nighttime Water Tank Shutdown from March 25-26


Town of Sunol Fire Suppression Project

PROJECT UPDATE 

Nighttime Water Shutdown

As part of the ongoing work on the water tanks on Tank Hill, we will take the tanks out of service at 10 p.m. on Wednesday, March 25 until 6 a.m. on Thursday, March 26. We will be connecting pipeline sections in order to bring the new tank into service.

What to Expect:

  • We do not anticipate any interruption in water service to the majority of our customers during this shutdown.
  • Some residences might experience low-water pressure during this time period.
  • Water service should return to normal Thursday, March 26at 6 a.m.

 

Look ahead

Although the majority of the work in the last two months has focused on Tank Hill, there will be some activity resuming in the Town. Now that the hydrants are live, bollards are installed, and the sidewalk crosswalk in front of the SFPUC- owned corporation yard has been repaired, there are only a few construction activities that remain in the Town before this project is complete.

Pavement Restoration

We will work with Alameda County and the contractor to repair any structural damage to the streets caused by construction.

Slurry Seal of Main Street

As promised, we will install a new slurry seal on Main Street, between Bond and Kilkare Road. This work is scheduled to begin during the week of April 6. It will take approximately three weeks to complete this work.   

What to Expect:

·         Work hours are 7 a.m. to 5 p.m. Please try to avoid the area during those times.

·         There will be no parking on Main Street during this time, and NO Parking signs will be posted prior to the start of this work.

·         Main Street will remain open to traffic, but please allow extra time to pass through the area.

·         The equipment and trucks related to this work will generate noise.  

 

 

Storage Tanks

Installation of the first of the two new replacement tanks on Tank Hill continues. Once the first new water storage tank on Tank Hill is placed into service (Spring 2015), the remaining pair of old, smaller water tanks will be demolished, and construction will start on the second replacement tank. Construction on Tank Hill will continue through summer of 2015.

 

Thank you for your patience!

As always, please do not hesitate to contact us with any questions, comments, or concerns.

24-hour Answering Line: (866) 973-1476

Visit our blog sfwater.org/sunolvalley for additional information.  


Tuesday, March 17, 2015

Heroes in a Half Shell at Calaveras Dam

We at the Calaveras Dam Replacement Project are constantly reminded that our construction area is someone else’s home. Case in point: the Western pond turtles (Actinemys marmorata). Our little heroes in the half shell are coming out of hibernation. A species of special concern in California, Western pond turtles prefer calm water with lots of things to bask on and plants to hide under.  They are opportunistic feeders and will eat pretty much anything they can reach and overpower, including aquatic plants, fishes, aquatic invertebrates and carrion if they can find it. They hibernate nearby in burrows or in upland areas until the temperature is nice, then they come out and head to the water to find food and mates.

Our construction workers spotted the first Western pond turtle of the season roaming on one of our haul roads. Given there are large vehicles (think trucks with wheels that are 9 feet tall), it was important to sweep this girl up and put her in a safe place away from the site. Our biological inspector Aaron Sunshine did just that at a pre-designated release site. On a daily basis, our environmental inspectors work closely with construction staff to identify any wildlife that enter the construction area. Our team works to protect the wildlife in the Watershed ensuring we keep these protected native species safe from harm while we build this important project.  

Maybe it was the luck of the Irish? Or just a good day for our Western pond turtle to be returned to a safe habitat. Aaron and his team will be keeping a sharp eye out! Happy St. Patrick's Day!

Peek-a-boo: Western pond turtle (measured at 16 cm carapace length) safely relocated at the Calaveras Dam Replacement Project by our project Environmental Monitor


Here is our Western pond turtle being released
safely back into the reservoir shoreline


Wednesday, March 11, 2015

Daylight Savings: San Antonio Reservoir at Dawn

Losing that hour of sleep for daylight savings last weekend was brutal.

SFPUC Watershed Keeper Pat Jones reminded us today of one small side benefit: he is out on his rounds before the sun comes up.





He shared this gorgeous photo of the SFPUC's San Antonio Reservoir in the Alameda Creek Watershed at dawn. 









San Antonio, like all of our reservoirs, is a protected, managed watershed that supports many rare and endangered plants and animals. No humans, though, with the notable exception of Pat.

See you around Sunol Valley!

Monday, March 2, 2015

The New Irvington Tunnel is officially in service!


Our teams are excited to announce that the New Irvington Tunnel is officially in service carrying drinking water to our 2.6 million Bay Area customers.

This is a major milestone since the completion of the New Irvington Tunnel Project completes the last three tunnels in the Water System Improvement Program (WSIP), creating a critical water lifeline able to withstand earthquakes on the Hayward, Calaveras, and San Andreas faults.

Located between the Sunol Valley and Fremont, the new seismically-designed tunnel is the last of three tunnels making up this “water lifeline” around the Bay.  The project is part of the agency’s $4.8 billion Water System Improvement Program.

The tunnel was constructed by the joint venture of Southland Tutor Perini who began tunneling in March 2011. It was constructed using conventional mining techniques from four separate headings using road headers and controlled detonation to break up the hard rock.
Tunnel Facts:
  • Tunnel Length: 18,660 feet or 3.5 miles
  • Location: Parallel to the existing tunnel between Sunol Valley and the City of Fremont 
  • Depth: Between 30 feet and 700 feet underground
  • Finished internal diameter: 8.5 feet
  • More than 7.8 million pounds injected into the tunnel
  • The New Irvington Tunnel will carry approximately 120 million gallons of water a day on average during normal operating conditions when both tunnels are in service.
  • The maximum amount of water the tunnel can transport per day: approximately 300 million gallons 
  • This project provided approximately 42% of total labor hours to SFPUC service territory residents, and nearly half (48%) of total apprentice hours to SFPUC service territory apprentices ensuring our local workers and local residents were able to participate in this unique, once-in-a-lifetime construction opportunity.
What Happens Next?

Now that the tunnel is in service, the construction team will begin restoration of the above ground facilities. The SFPUC will take the existing tunnel out of service for inspection in early March 2015. The entire New Irvington Tunnel Project will be complete in Fall 2015.

1933: Historic photo of  worker at Irvington Portal spherical manifold

Today: New Irvington Tunnel worker at new dishhead at Irvington Portal

Friday, February 20, 2015

Last of the Pipe Installed at New Irvington Tunnel

The crews have reached a major milestone and installed the last of the pipe for the New Irvington Tunnel.  A 35 ft section of steel pipe was prepped and mortar lined at the surface before being lowered into the Vargas Shaft. This officially completes the entire 3.5 mile water transmission tunnel.  Final steps are being made the next week to disinfect the tunnel and bring it into service to provide a seismically designed connection to provide water to our 2.6 million Bay Area customers.