Construction Update- Sept. 4, 2014
Pipe main installation has been completed on Main St., Bond St., Foothill, and Kilkare Roads. Additional digging will take place when the fire hydrants are installed. What is next for this project?
Railroad Crossings
*During the week of September 8, we anticipate starting the jack and bore work underneath the Union Pacific Railroad on Main Street. This crossing should be complete in approximately three weeks.
* The crossing underneath the Alameda County Railway at the intersection of Foothill Road, Kilkare Road and Main Street should begin at the end of September or early October.
What to Expect during Jack and Bore Work
* Crews will dig a deep pit on both sides of the railroad, and they will insert pipe from the driving pit near the Antique Store to the receiving pit in front of the Post Office Driveway.
* Main Street will be reduced to one-lane traffic at the railroad crossing. We appreciate your patience with the expected traffic delays in the area.
* Access to the Sunol Post Office will be open at all times.
Pleasanton Sunol Road
* Work on Tank Hill will continue as crews construct the foundations for the new tanks and construct new pipe connections up the hill.
* We will lay pipe cross Pleasanton Sunol Road during the evening of Thursday, September 5, starting at approximately 8:00 p.m. through 5:00 a.m. on Friday, September 6. Traffic will be one-lane through this area during this time.
Bridge Crossings
Crews will lay pipe across the bridges at Sinbad Creek on Bond Street towards the end of September followed by the bridge on Foothill Road and Kilkare Road.
Hydrant Installation
Hydrants will be installed at the marked locations as the contractor’s schedule allows.
Thursday, September 4, 2014
Friday, August 22, 2014
Construction Advisory: New Irvington Tunnel Irvington Portal
We wanted to inform you of some very
important construction activity affecting the neighborhood at the Irvington
Portal site off Mission Boulevard.
Irvington Portal work August 27 – September 15:
As part of the process of preparing the tunnel to be brought into service, we will need to provide additional tunnel ventilation to our construction crews at the Irvington Portal site. The equipment will begin mobilizing in the area on August 27, 2014, and work should be complete by September 15, 2014. The ventilation equipment, which includes a fan and generator, will operate 24 hours a day. Cooling air is needed for crews who are lining the tunnel with a cement mortar to prepare it for being put into service. The sound barrier walls will keep the noise to a minimum and the contractor will install additional noise reduction measures.
As part of the process of preparing the tunnel to be brought into service, we will need to provide additional tunnel ventilation to our construction crews at the Irvington Portal site. The equipment will begin mobilizing in the area on August 27, 2014, and work should be complete by September 15, 2014. The ventilation equipment, which includes a fan and generator, will operate 24 hours a day. Cooling air is needed for crews who are lining the tunnel with a cement mortar to prepare it for being put into service. The sound barrier walls will keep the noise to a minimum and the contractor will install additional noise reduction measures.
Disinfection Process starting October 2014:
Starting the first week of October, we will begin the disinfection process to bring the New Irvington Tunnel into service. In order to disinfect the tunnel, crews will need to stage generators and lights for the 24 hour a day filling/disinfection. The set up will occur during day light hours. The filling/disinfection process will take 2-4 days to complete once it begins. The expected night time activities should be limited to three nights.
Starting the first week of October, we will begin the disinfection process to bring the New Irvington Tunnel into service. In order to disinfect the tunnel, crews will need to stage generators and lights for the 24 hour a day filling/disinfection. The set up will occur during day light hours. The filling/disinfection process will take 2-4 days to complete once it begins. The expected night time activities should be limited to three nights.
What Happens Next?
The New Irvington Tunnel is anticipated to be in service delivering water sometime in November. The above ground work and restoration will continue into early 2015. These include final installations and burial of the new portal facilities, construction of a new security bunker at the existing tunnel portal (on top of the hill), and site restoration work, planting and fencing. The remaining sound walls will be removed after the entire site is restored.
The New Irvington Tunnel is anticipated to be in service delivering water sometime in November. The above ground work and restoration will continue into early 2015. These include final installations and burial of the new portal facilities, construction of a new security bunker at the existing tunnel portal (on top of the hill), and site restoration work, planting and fencing. The remaining sound walls will be removed after the entire site is restored.
Project Background
The New Irvington Tunnel Project is part of the $4.6 billion Water System Improvement Program (WSIP) to repair, replace, and upgrade our system’s aging pipelines, tunnels, and dams. The new 3.5 mile long tunnel will provide a seismically-designed connection between water supplies from the Sierra Nevada Mountains and the Alameda Watershed to Bay Area water distribution systems. Final construction is expected to be complete in 2015.
The New Irvington Tunnel Project is part of the $4.6 billion Water System Improvement Program (WSIP) to repair, replace, and upgrade our system’s aging pipelines, tunnels, and dams. The new 3.5 mile long tunnel will provide a seismically-designed connection between water supplies from the Sierra Nevada Mountains and the Alameda Watershed to Bay Area water distribution systems. Final construction is expected to be complete in 2015.
Questions / Concerns?
We greatly appreciate your patience. Please call our 24-Hour Answer Line at 866-973-1476 or email mle@sfwater.org or blauppe@sfwater.org if you have any questions.
Follow us online at sfwater.org/sunolvalley
We greatly appreciate your patience. Please call our 24-Hour Answer Line at 866-973-1476 or email mle@sfwater.org or blauppe@sfwater.org if you have any questions.
Follow us online at sfwater.org/sunolvalley
.
Friday, August 15, 2014
Why we should all be excited about Cement Mortar Lining
The
really big news from the team constructing the New Irvington Tunnel – a seismically
designed crucial tunnel between Sunol Valley and Fremont and our 2.6 million
Bay Area customers – is that installation of the cement mortar lining has
begun! Although this may seem like a
good time to yawn, this is actually really exciting news! Here’s why.
It
is one of the final stages of constructing a water tunnel before we bring it
into service. The New Irvington Tunnel
is 95% complete, and we hope to bring the new tunnel into service this
fall. Now are you more excited?
First
we excavated the tunnel from four different locations using road headers and
drill and blast methods. Then we inserted steel pipe final liners into the 3.5
mile long tunnel. We welded the pipe together and injected grout in the space
between the pipe and the tunnel to seal it off from groundwater intrusion along
the entire 3.5 mile length.
There
is still work left to be done before water delivery can begin, but cement
mortar lining application is a key step to prevent corrosion of the steel pipe
and prepare it for water conveyance. Our
workers will use specialized equipment that sprays cement on the pipe’s
interior and creates a very smooth surface.
Mortar Lining being applied in the New Irvington Tunnel
Installation of the mortar lining should take about two months. After that we will complete the
pipeline connections on both ends of the tunnel and install rounded dishhead
caps on the end of the pipe. Then SFPUC
Operation crews will disinfect the entire pipe, flush it and bring it into
service by the end of October 2015. Surface
work and restoration will then take up the remaining months of the project. We
anticipate being done in summer 2015.
So
although the words “mortar lining installation” might not stop traffic, it is
music to our ears!
Friday, August 8, 2014
Town of Sunol Fire Suppression Project Update
Kilkare Road, here we come!
Construction has begun to improve the water distribution
system and fire hydrants in the Town of Sunol. The project includes
constructing two miles of new pipelines on County roads, installation of
approximately 26 new fire hydrants, and replacing the existing water tanks that
serve the Town of Sunol.
Here’s
an update, hot off the presses as of August 8, 2014
- What we’ve completed to date: Construction Crews have installed new pipeline on Main Street, Bond Street, Foothill Road West and East of Kilkare Road, and at Sunol Glen School. Hydrant locations have also been staked in these areas as well.
- What’s next: Starting the week of August 11, 2014, our crews will next start pipeline installation on Kilkare Road, starting at the intersection with Foothill Road, and moving all the way up to the ‘600 block’ of Kilkare Road. Pipeline installation on Kilkare should be completed by Labor Day.
- Hydrant Installation: Hydrants will be installed at marked locations during this time period as the contractor’s schedule allows.
What
will come after that? Construction Look-ahead for September 2014:
- Jack and Bore Crossing underneath Alameda County Railway at the intersection of Main Street, Kilkare Road, and Foothill Road.
- Jack and Bore Crossing underneath Union Pacific Railroad on Main Street is scheduled to start at the end of September.
What
to Expect during Construction:
- One-lane traffic through construction zones during work
hours. This will cause some delays, so
please plan ahead.
- Work Hours: 7:00 a.m. to 5:00 p.m.
- Limited Work on Saturdays for a small crew to install
hydrants.
- Night work will be necessary during pipeline/tank
shutdowns. We will minimize noise.
- Access to private driveways and around streets will be
available at all times.
Stay in Touch:
24-hour Answering Line:
(866) 973-1476
Visit our blog sfwater.org/sunolvalley
Thank you so much for your patience and kind
consideration during construction!
Labels:
Sunol,
Sunol Fire Suppression,
Sunol Valley,
Town of Sunol
Thursday, July 31, 2014
Construction Update: Town of Sunol Fire Suppression System Project
Construction has begun to improve the water distribution system and fire hydrants in the Town of Sunol. The project includes constructing two miles of new pipelines on County roads, installation of approximately 26 new fire hydrants, and replacing the existing water tanks that serve the Town of Sunol.
Two Important Construction Updates:
1) There has been a shift in the project schedule. The pipeline installation on West Foothill Boulevard (west of Kilkare Road) has been moved up to the week of August 4th, and should be completed by August 13th. Please expect delays in the area (see map).
Upcoming work: Construction on Lower Kilkare Road from this intersection will begin shortly thereafter in mid-August. Finally, the jack and bore crossing underneath the Alameda County Railroad at the intersection of Main Street and Kilkare Road is expected to begin in mid-August as well.
2) Water Tank Shutdown. In order to begin work on tank hill, crews will be taking the water tanks that service the town out of service from 11 p.m. Monday, August 4, 2014 until 5:00 am. Tuesday August 5, 2014. SFPUC customers should not experience a loss in water service, however some residences might experience lower water pressure during this nighttime period. Water service should return to normal the morning of August 5, 2014. The shutdown has been scheduled at night to minimize inconvenience.
If you should have any questions at any time, please do not hesitate to contact us at our 24-hour hotline (866) 973-1476 or epowell@sfwater.org; blauppe@sfwater.org.
Thank you for your patience during construction!
Two Important Construction Updates:
1) There has been a shift in the project schedule. The pipeline installation on West Foothill Boulevard (west of Kilkare Road) has been moved up to the week of August 4th, and should be completed by August 13th. Please expect delays in the area (see map).
Upcoming work: Construction on Lower Kilkare Road from this intersection will begin shortly thereafter in mid-August. Finally, the jack and bore crossing underneath the Alameda County Railroad at the intersection of Main Street and Kilkare Road is expected to begin in mid-August as well.
If you should have any questions at any time, please do not hesitate to contact us at our 24-hour hotline (866) 973-1476 or epowell@sfwater.org; blauppe@sfwater.org.
Thank you for your patience during construction!
Tuesday, July 29, 2014
California red-legged frog: Our Newly Famous Sunol Valley Resident
Just a few
weeks ago, Governor Jerry Brown signed legislation designating one of our local
Sunol Valley animals -- the California red-legged frog -- as the official State
Amphibian! Since getting an autograph is out of the question, we thought we’d
offer you a reintroduction to our famous resident instead.
The
California red-legged frog is the largest native frog in the state and was
first made famous in Mark Twain’s The Celebrated Jumping Frog of Calaveras
County. According to the
National Wildlife Federation, true to its name, they have reddish coloring on
the underside of their legs and belly. They dine on anything they can catch and
fit into their mouths. Mostly insects, but the occasional amphibian or small
mammal might also become dinner. Speaking of dinner, California red-legged
frogs were once a popular dinner cuisine during the Gold Rush era.
Contra Costa
and Alameda Counties contain the majority of known observations of California
red-legged frogs in the San Francisco Bay Area (U.S. Fish and Wildlife Service
2002). Today, their existence is threatened due to
loss of habitat, particularly near urban communities and development.
Thankfully, the 36,000 acres of Southern Alameda Creek Watershed lands owned by
the San Francisco Public Utilities Commission has been protected and is a haven
for our famous residents.
Our primary goal
as watershed stewards is to protect existing populations, control non-native
predators, and protect habitat for the red-legged frogs. As we make progress on
our Water System Improvement Program in Sunol Valley, our Environmental
Compliance teams work side by side with construction contractors to ensure our
newly-designated Official State Amphibian is safe from harm.
Photos courtesy of Bill Stagnaro, Environmental Inspector
with the Calaveras Dam Replacement Project
Friday, July 25, 2014
We are halfway there!
The Calaveras
Dam Replacement Project team reached an important milestone
for the project this week. Crews have excavated more than 5.4 million cubic yards of earth
and rock material at the project site. This material would fill approximately 1,656 Olympic-sized swimming
pools. A total of 10 million cubic yards of material is required to be moved for the entire
project--- 6.5 million cubic yards to be excavated and 3.5 million cubic yards which will go into the construction of the new dam. In addition, 10,000 cubic
yards of concrete to date has been poured and placed in the new intake tower and the new spillway
structure. Much work still lies ahead, but definitely something to celebrate for our hard working crews from Dragados USA /Flatiron/Sukut Construction Joint Venture.
Crews gather to celebrate reaching over 5 million cubic yards of earthen materials excavated
Concete work at the new spillway underway