Thursday, October 16, 2014

Sunol Valley: Getting Prepared – Seismic Upgrade Work Continues

Much has already been done as mentioned in our last post, but more important work lies ahead in Sunol Valley.  Our teams continue critical work to seismically upgrade our infrastructure. As we remember the Loma Prieta earthquake this week, here are some highlights on our ongoing projects:

New Irvington Tunnel Project
The new tunnel will provide a seismically upgraded connection between water supplies from the Sierra Nevada Mountains and the Alameda Watershed to Bay Area customers. It will extend 3.5 miles and have an internal diameter of approximately 8.5 feet. Final completion is expected in mid-2015.



Calaveras Dam Replacement Project
Work continues to build a replacement dam that will be seismically safe and restore the Calaveras reservoir to its historic capacity. The reservoir provides half of the Hetch Hetchy Regional Water System’s local Bay Area water storage. To date, over 5 million cubic yards of materials have been excavated and major work is being done on the new spillway. 
Final completion is expected end of 2018. 



San Antonio Backup Pipeline Project
The San Antonio Backup Pipeline (SABPL) project will include several new facilities and improvements in the Sunol Valley to help provide for the reliable movement of Hetch Hetchy water for planned and emergency discharges under future conditions. Completion is expected in March 2015.


We are extremely proud of our hard working teams in Sunol Valley, helping all of us become better prepared for the next earthquake. For more info, please contact us at our 24 hour answer line 866-973-1476.


Tuesday, January 14, 2014

What’s on Tap for the Sunol Valley in 2014?

A few weeks into the New Year, our Sunol Valley Project teams are already very busy with the important work to seismically upgrade facilities which deliver drinking water to 2.6 million Bay Area customers as part of the Water System Improvement Program (WSIP) and other ongoing projects. Here’s a quick snapshot of the anticipated activities of the year to come. Please visit us often on our blog to stay up to date and learn more!

New Irvington Tunnel
In October 2013, we completed excavation of the new tunnel.  Recently, the project team began installing the inner lining for the tunnel. These are 50-foot-long, 8½ foot in diameter steel pipes that are inserted into the tunnel on a special train. Once in place, these pipe segments are welded together from the inside.  On average, seven pipe sections are installed daily.  Project completion is anticipated for 2015.

50 ft. pipe being prepared for installation at New Irvington Tunnel


Calaveras Dam Replacement Project
The largest project in the Sunol Valley continues with ongoing major excavation as well as drill and blast activities to stockpile materials in preparation for the construction of the replacement dam.  We are still clearing out loose soil and rock materials in the area to make room for the new dam. In the coming weeks, the project will begin construction of the new 1,550-foot-longspillway, all the while dealing with the continuing challenges of the site’s complex geology. Grouting work on the left abutment of the new dam will also begin soon.  As construction progresses, the environmental team continues to find and catalogue interesting fossils at the site. Projected completion is anticipated in 2017.
Aerial view of upper Left Abutment for Replacement Dam
(left side of valley when looking downstream)

San Antonio Backup Pipeline
Construction of the San Antonio Backup Pipeline, which will add operational flexibility to our Sunol Valley Water transmission system, has been moving forward towards completion in March of 2015.  The majority of the new pipeline has been installed and is in the ground.  The new slurry wall was also completed last year.  This year the project team will focus on construction of the small above-ground structures and discharge pumps at the quarry storage pond at the north end of the site.

Workers excavating and shaping the hillside in preparation
for the outfall structure that will be going into Pond F3-east

Town of Sunol Fire Suppression System Project
2014 will see the start of construction of this important public safety project in the Town of Sunol.  The SFPUC will upgrade the water distribution system for the Town of Sunol since the current system is inadequate.  The SFPUC will add additional fire hydrants in commercial and residential areas of the Town of Sunol, replace pipelines on County roads to improve the flows from the fire hydrants, and also replace two to four of the Town's existing water storage tanks on the hill.  Construction for this project is anticipated to start spring/summer of this year.

Alameda Creek Watershed Center and Sunol Yard Upgrade
Plans are underway to design and construct the Alameda Creek Watershed Center located near the Sunol Water Temple, as part of its efforts to improve the existing facilities in the Sunol Yard. The proposed Watershed Center would provide a place for people to gather and learn about the Alameda Creek Watershed, its natural resources and its role as part of the SFPUC water supply system as well as connect with the history of the Sunol Valley.  This project is in its early planning and design stages with construction anticipated to begin in 2015. 

Bioregional Habitat Restoration
Construction activities for the Bioregional Habitat Restoration (BHR) program will start winding down this year. We will, however, continue to monitor the success of these projects through 2024. The projects that are nearly completed within the Sunol Valley  -- Goldfish Pond Restoration at the southern end of Calaveras Road, San Antonio Creek Restoration, Sheep Camp Creek and Goat Rock – have restored or enhanced a combined total greater than 1,500 acres of sycamore and oak riparian woodland, oak woodland and savannah, and serpentine and annual grasslands.

This project includes restoring 5,000 feet of the existing Sheep Camp Creek.

Completed Projects
As we start 2014, we can also continue to celebrate the completion of the Sunol Valley Water Treatment Plant Expansion and Treated Water Reservoir project in September 2013. This water treatment plant now enables us to filter and provide 160 million gallons of water per day to our Bay Area customers for up to two months should our Hetch Hetchy Reservoir supplies become unavailable due to an earthquake or other emergency.

We look forward to working with you this year and all the good things to come to Sunol Valley!

Thursday, May 9, 2013

What are We Building along Calaveras Road?

Those who frequently travel on Calaveras Road in the Sunol Valley will likely notice increased activity along the west side of Calaveras Road, south of Interstate 680 (I-680). It is, in fact, the latest Water System Improvement Program Project to begin construction in the Sunol Valley - the San Antonio Backup Pipeline Project. Construction officially began in April, and the contractor, Ranger Pipelines Inc., has begun mobilization activities.

What are we building?
  • Approximately 1.3 miles of 5 ½ foot diameter pipeline
  • New chemical storage, feed, and equipment facilities
  • A new cut-off wall around one of the quarry pits located just south of I-680.
  • The contractor will also complete upgrades to the water delivery pipeline that serves the Town of Sunol.
What to Expect
  • Trucks entering and exiting the project driveway site, along Calaveras Road approximately 1/3 of a mile south of I-680 along Calaveras Road.
  • Intermittent delays are possible during construction on Calaveras Road.
  • Please proceed with caution when travelling through construction zones.
  • Additional construction activity on the west side of Calaveras Road.
  • All construction activities will occur on SFPUC-owned property.

Project Location Map
Alignment for San Antonio Backup Pipeline is in red.
Work Hours
  • Monday – Friday: 7:00 a.m. to 5:00 p.m.
  • No planned work on weekends or holidays.
Why are we building this?
Two-way traffic is better, at least in the case of the San Francisco Public Utilities Commission’s (SFPUC) San Antonio Pipeline. The existing San Antonio Pipeline acts as a water transmission pathway in the Sunol Valley. This pipeline allows us to discharge Hetch Hetchy water to San Antonio Reservoir for storage and send reservoir water to the Sunol Valley Water Treatment Plant for treatment before distribution to customers. The problem is that there is currently only one pipeline, so water can only move in one direction at a time.

When complete in 2015, the San Antonio Backup Pipeline will enable the SFPUC to discharge Hetch Hetchy water to a nearby quarry pit during emergency events while at the same transporting San Antonio Reservoir Water to the Treatment Plant at the same time. This adds operational flexibility to the system and minimizes the risk of service disruption to 2.6 million customers.

See you around the Sunol Valley!