Monday, October 29, 2012

Teamwork pays off

It’s not quite like a Giants baseball game out here, but our crews at the Calaveras Dam Replacement Project sure know a thing or two about the importance of teamwork.  Just like base coach Tim Flannery uses hand signals to communicate on the field, our Calaveras Dam workers use the same method to communicate to each other at the site.

Since Friday, we started filling concrete in the new shaft which is an important function for the new Calaveras Dam.  The shaft is part of the new intake tower which moves water from the Calaveras Reservoir through the adit tunnels eventually treated to become our drinking water. The level of noise and limited visibility in the shaft can be challenging, so our workers rely on hand signals and radio communication to mobilize.  Our workers signal the crane to lower a bucket full of concrete into the shaft, and then workers below fill the wall forms with concrete.

The shaft is 152 feet deep and over 720 cubic yards of concrete will be placed once it is completed. It takes approximately a week for the concrete to reach a specified strength before continuing, therefore the concrete work will be completed in 16 foot lifts at a time through March 2013.

Worker signals crane to move concrete bucket into shaft

Top of the Shaft 
 
Workers in Shaft below with Concrete Bucket

For the San Francisco Giants, teamwork wins championships.  As for our workers, teamwork builds progress for the Calaveras Dam Replacement Project.  Congrats to both teams!  For more project info, contact us at our 24 hour answer line at (866) 973-1476 or email mle@sfwater.org
 
Photo Courtesy Fox News

Thursday, April 26, 2012

Calaveras Dam Tunneling Away

Tunneling is a daily occurrence for other Water System Improvement Projects like our neighbors at the New Irvington Tunnel; as of today the Calaveras Dam Replacement project has reached approximately 65 feet in tunneling for one of our three adits for the Calaveras Dam.
The new intake shaft will be excavated vertically about 200 feet in total. Entering through our new intake shaft, our team utilizes a roadheader, a piece of excavating equipment used to break through bedrock by drilling horizontally. Today, our new adit has successfully reached the existing intake tower, which connects the Calaveras reservoir water supply to the rest of our water infrastructure system. The adits function as connecting tunnels between the reservoir water which is fed through the intake tower and is eventually treated to supply our drinking water. The three adits, located at different levels, are able to transport water at different reservoir levels. Work will begin on the second and third lower adits as the shaft excavation progresses. Our team continues to comply with all the required safety requirements, utilizing a ventilation system through the duration of the tunnel work. View of roadheader looking down into new intake tower:
For more project info, contact us at our 24 hour answer line at (866) 973-1476 or email mle@sfwater.org