Calaveras Road Reopens January 3, 2019


We are pleased to inform you that Calaveras Road between Geary Road and Felter Road will reopen to all traffic, weekdays, weekends, and holidays starting Thursday, January 3, 2019 at 10:00 a.m. 

Please note construction trucks and large vehicles will still be using the road, so please drive and ride with caution.

Background:
The San Francisco Public Utilities Commission (SFPUC), owner and operator of the Hetch Hetchy Regional Water System, is completing construction of a new dam to replace the former 93-year-old Dam at Calaveras Reservoir in the Sunol Valley.

Restoring Calaveras Reservoir is one of the most important projects of the $4.8 billion Water System Improvement Program. Calaveras Reservoir is the Hetch Hetchy Regional Water System’s largest Bay Area reservoir when it is full. Restoring its historic levels is crucial for water supply to 2.7 million people in the Bay Area in times of drought and emergencies. Construction on the earth and rock fill dam began in 2011.  Construction is scheduled to be complete in spring 2019.

Contacts:

For more information, visit sfwater.org/calaverasroad

We thank you for your patience!



Thursday, September 27, 2018

Calaveras Road Closure Extended through November 2, 2018



The Closure of Calaveras Road to through traffic between Milpitas and Sunol has been extended from September 30, 2018 to Friday, November 2, 2018.

The road will reopen to all traffic, weekdays, weekends, and holidays starting Saturday, November 3, 2018.

Why:

The SFPUC has been working with the appropriate county agencies to secure final approval for renewed public access to the road after a portion of the road was built by the SFPUC to replace a portion undermined by a landslide.

Background:

We have been working since 2011 to replace the 93 year-old Calaveras Dam to increase the reliability of the Hetch Hetchy Regional Water System, which serves 2.7 million people in four Bay Area counties.

The closure of Calaveras Road began in July 2016 to protect public safety on the extremely narrow portions of Calaveras Road while large trucks utilized the road for construction.  

Road Closure Details:

Where: Calaveras Road just south of Geary Road (entrance to Sunol Regional Wilderness) to Oakridge Road near the Alameda /Santa Clara County line.

When: July, 2016 through November 2, 2018. The Road will be open on weekdays, weekends, and holidays starting Saturday, November 3, 2018.

For more information, visit sfwater.org/calaverasroad

Thank you for your continued patience. We apologize for the inconvenience.

Friday, January 27, 2017

Photo Friday: Bobcats on Calaveras Road


Here is a recent photo taken by our Watershed Keeper Pat in Sunol Valley. It was a reminder about the amazing wildlife out here in the Alameda Creek watershed and to keep a look out for them on the roads.

Just a reminder that due to storm damage, Calaveras Road remains CLOSED to all types of thru traffic 7 days a week, 24 hours a day, between Geary Road and Oakridge Road near the Alameda/Santa Clara County line.

Under normal conditions and the construction schedule, Calaveras Road would be open to thru traffic on weekends and holidays. However, at this time the road will remain closed every day to all traffic until further notice.

The entrance to East Bay Regional Park District's Sunol Regional Wilderness will be open at all times from the north.

Visit www.sfwater.org/calaverasroad for more details and for a map of the closure.

Thursday, January 12, 2017

ALERT: FULL CLOSURE OF CALAVERAS ROAD DUE TO STORM DAMAGE


FULL CLOSURE OF CALAVERAS ROAD DUE TO STORM DAMAGE

EFFECTIVE THURSDAY, JANUARY 12, 2017
CLOSURE IN EFFECT 7 DAYS A WEEK, 24 HOURS A DAY 



What:
Effective January 12, 2017, a full closure of Calaveras Road to all types of thru traffic 7 days a week, 24 hours a day between Geary Road and Oakridge Road – near the Alameda/Santa Clara County line. 
This is due to storm damage along this stretch of road. Under normal conditions and the construction schedule, Calaveras Road would be open to thru traffic on weekends and holidays. However, this is no longer the case, and the road will remain closed every day to all traffic until further notice. 
Please avoid this area and use alternative routes.

Where:
The portion of Calaveras Road just south of Geary Road (location of entrance to Sunol Regional Wilderness) to Oakridge Road – near the Alameda/Santa Clara County line.

When:
The closure will take place 7 days a week starting on January 12, 2017 and will remain in place until further notice. We are working with local responding agencies on this issue, and will keep you informed as we get additional information.

Please note: the entrance to East Bay Regional Park District’s Sunol Regional Wilderness will be open at all times from the north.

If you have any further questions, feel free to call our toll-free 24 hour answer line at
(866) 973-1476.







Wednesday, December 14, 2016

Holiday Construction Schedule and Calaveras Road Closure for Sunol Valley

Happy Holidays, Sunol Valley!

Here’s a schedule of where we’ll be working over the holiday season.

Calaveras Road Closure Holiday Schedule:

The portion of Calaveras Road Currently Closed to the public on weekdays will be:
  • Thursday, December 22, 2016 at 8:00 PM through Monday, December 26, 2016   OPEN to the public 
  • Tuesday, December 27, 2016 at 4:00 a.m. through  Friday, December 30, 2016:  CLOSED
  • Saturday, December 31, 2016 at 5:00 AM through Monday, January 2, 2017: OPEN to the public
  • Tuesday, January 3, 2017 at 4:00 a.m. – Friday, January 6, 2017: CLOSED
Prior to the road opening to the public, the road will be swept of debris.

Weekday closures will continue as planned Monday- Friday through December 31, 2017

Fish Passage Facilities Project within the Alameda Creek
Located in Sunol Regional Wilderness:

The project team will NOT be working:

December 24, 2016  to December 26, 2016

December 31, 2016 to January 2, 2017

As always please don’t hesitate to contact us at 866-973-1476, or mle@sfwater.org or blauppe@sfwater.org with any questions.



Tuesday, November 22, 2016

Sunol Valley Construction Updates for the Thanksgiving Weekend


The wild turkeys are out and about at the Calaveras Dam Replacement Project. For the upcoming Thanksgiving Holiday weekend, we wanted to share with you some reminders for our projects:

Calaveras Road Users:
The closed portion of Calaveras Road will be OPEN to the public this Thanksgiving Holiday on November 24, 2016 and the day after Thanksgiving on November 25, 2016. The road will be closed again on Sunday, November 27, 2016 at 11:00 p.m.

Please see more details by visiting www.sfwater.org/calaverasroad
Thank you for your ongoing patience during our road closure.


Calaveras Dam Replacement Project
Constructions crews are off on the Thanksgiving  Holiday on November 24, 2016 and the day after Thanksgiving on November 25, 2016. Regular work will resume on November 28th.

Fish Passage Project within Alameda Creek Watershed
Constructions crews are off this week and there will be no construction activity at the Fish Passage project site located in Sunol Regional Wilderness Park. Regular work will resume on November 28th.

From all of the construction teams, we hope you have a wonderful holiday weekend!

Thursday, June 30, 2016

Sunol Valley Updates: Calaveras Road Closure and Construction Updates

Here are some important updates that may affect you:

Calaveras Road Closure Starts July 5th

To those who drive or ride Calaveras Road between Milpitas and Highway I-680 through the Sunol Valley: Please take note that Calaveras Road will be closed between Geary Road (just south of the entrance to Sunol Regional Wilderness) to Oakridge Road (near the Santa Clara / Alameda County line) starting July 5, 2016 for 18 months for safety reasons. The closure is weekdays only. 

Why Close the Road?
Although the majority of the materials for the new dam will come from on-site, approximately 300,000 cubic yards of sands and gravels and 150,000 cubic yards of hard rock will need to be imported to the site for construction of the dam. These materials will be imported in large hauling trucks on Calaveras Road. At its peak, truck traffic could amount to an average of one haul truck every five minutes on Calaveras Road during heavy hauling activities. It is not safe for this many large trucks to share the narrow portions of Calaveras Road with cyclists and private vehicles. 

Road Closure Details
  • Where: Calaveras Road just south of Geary Road (entrance to Sunol Regional Wilderness) to Oakridge Road – near the Alameda / Santa Clara County line.
  • When: weekdays ONLY
  • The road will be swept of debris before opening at 6 a.m. on Saturday mornings
  • The road will be closed every Sunday evening at 11:00 p.m.
  • Gates: Two gates will close Calaveras Road just south of Geary Road and at Oakridge Road
  • Emergency First Responders will have access through the closure at all times
  • The entrance to East Bay Regional Park District’s Sunol Regional Wilderness will be open at all times from the north
  • The road will be OPEN on weekends, for specific cycling races and for major holidays.
To learn more about the Calaveras Road Closure, please visit sfwater.org/calaverasroad for more details

Construction Activity to begin in the South end of the Calaveras Reservoir

What
Staring July 5, 2016 thru Mid 2018, increased construction activity will begin in the southern end of Calaveras Reservoir which the project refers to as Borrow Area E. In order to construct the replacement dam, we will need to gather clay materials from Borrow Area E.

What to expect
  • Construction vehicles and earth moving machinery working at the southern edge of the reservoir on SFPUC property.
  • Typical work hours are from 6:00 am to 6:00 pm
  • You may hear back up alarms and some noise from the equipment
  • Traffic: the trucks will stay off public roads for construction work. They will utilize specially-constructed roads within SFPUC property instead
  • The project will not use Marsh or Felter Roads to access the construction areas or to haul materials. 

No Construction Work on the 4th of July
Our construction crews in Sunol Valley will not be working.
We hope everyone has a safe and wonderful Independence Day. 




Thursday, May 26, 2016

Sunol Valley Teams Celebrate Memorial Day


In observance of Memorial day, our construction teams will not be working on May 30th at the Calaveras Dam Replacement Project or the Fish Passage Facilities within the Alameda Creek Watershed Project in Sunol Valley.

We hope all of you have a safe and wonderful Memorial Day weekend.

Schedule Update for Calaveras Road Closure
To those who drive or ride Calaveras Road between Milpitas and Highway I-680 through the Sunol Valley:

The SFPUC has postponed the start of the closure of Calaveras Road, which was originally planned to begin on June 1, 2016. We will continue to keep you up-to-date on the timing and status of the closure. Calaveras Road is currently open to the public.

It is important to note that there is still truck traffic on Calaveras Road now between I-680 and the entrance to Calaveras Dam. The speed limit is 25 mph on Calaveras Road in construction zones. Please ride and drive safely on the narrow portions of Calaveras Road.

Follow the Calaveras Road closure updates online at sfwater.org/calaverasroad

To receive email notifications, please email mle@sfwater.org


Thursday, March 31, 2016

Calaveras Road Traffic Advisory - Increased Haul Truck Traffic Starting April 4th

Please expect increased truck traffic on Calaveras Road beginning April 4, 2016 through April 29, 2016 during daytime hours. The project will haul materials from 6:00 am to 6:00 pm. Night hauling also continues through June 1st which begins approximately from 6:00 pm to 4:00 am, Monday through Friday.

This affects the portion of Calaveras Road between the I-680 entrance in Sunol to the entrance of the construction site for the Calaveras Dam Replacement Project located south of Geary Road. Commuters may experience periodic delays. Cyclists: please try to avoid this area if at all possible to remain safe.
 
  • Calaveras Road remains open to the public
  • Increase in haul trucks expected between the hours of 6:00 a.m to 4:00 a.m Monday thru Friday
  • Please drive and ride safely on the narrow portions of Calaveras Road and expect delays
  • Speed limit is 25mph in construction zones
 

March 2016 Aerial of Calaveras Dam Replacement Project 

24 hour- Answer Line: 866-973-1476
mle@sfwater.org or blauppe@sfwater.org

Wednesday, January 23, 2013

Calaveras Road Construction Advisory: 1/24/13 - 1/25/13 Truck Traffic

The Calaveras Dam Replacement Project will be expecting additional haul truck traffic on:
January 24 & January 25, 2013  just south of Interstate 680 to the project site approximately 4 miles past Geary Road.

·         Road remains open to the public
·         Haul trucks are expected from 7:00 a.m. to 4:00 p.m.
·         Please drive and bike safely on the narrow portions of Calaveras Road Speed limit is 25 mph in construction zones
                                                                                                                                                                                     
For More Information:
24 hour-Answer Line 866-973-1476
Email us:
Follow us online at: Sfwater.org/sunolvalley

Monday, December 10, 2012

Calaveras Dam Replacement Project - Winter Update

Project Update
In mid- June of 2012, during excavation of the large hill known as “Observation Hill” on the left side of the valley (if you are looking downstream, standing with your back to the reservoir), the Contractor encountered unexpected geologic conditions that could contribute to the instability of the left abutment and spillway area as designed.  These features were not visible at the ground surface, and were not apparent during the extensive pre-construction geotechnical investigations. Therefore, the excavation cut slope in “Observation Hill” has been re-designed to “lay back” the slope to a flatter slope in order to produce a final slope that will be stable during construction and over the entire life of the new dam.


What this Means
1)    Additional Materials to Move - Approximately 3 million cubic yards of additional material that was not originally anticipated now needs to be excavated and moved to disposal sites around the reservoir. We are working with the environmental regulatory agencies to secure disposal sites for these materials within the designated construction areas. No additional materials will be hauled off site on public roads.

2)    Extended Construction Schedule - Because of the additional time needed to excavate these additional materials, we anticipate a 25 month delay in the project, which would put the completion of construction activities at the end of 2017.

3)    Impact to Project Cost, not to WSIP Overall Cost – Based on preliminary projections, the cost of the project will increase by approximately $133 million. These additional costs are offset by savings recorded on other projects and favorable bond financing so the overall Water System Improvement Program (WSIP) is still forecasted to be completed within the currently approved budget of $4.6 billion.

4)    Calaveras Road Shutdown Delayed - The second scheduled closure of Calaveras Road will be postponed until 2014, at the earliest. The duration of the closure remains 18 months, Monday through Friday only, but the specific dates will be determined when the contractor completes re-sequencing of the construction schedule.  We will notify you in advance of the closure period.  Join our road closure notification mailing list by emailing: mle@sfwater.org or calling our 24 hour answer hotline at (866) 973-1476.
Environmental Review
We are currently working with the regulatory agencies to amend the permits for these changes. The San Francisco Planning Department will distribute an Addendum to the Final Environmental Impact Report in mid-December 2012. To obtain a copy of the Addendum, please visit www.sf-planning.org, or contact: Chris Kern, San Francisco Planning Department at (415) 5759037 or email at chris.kern@sfgov.org.
Project Background
The San Francisco Public Utilities Commission, owner and operator of the Hetch Hetchy Regional Water System, is building a new dam to replace the existing Calaveras Dam in the Sunol Valley. Calaveras Reservoir, impounded by the Calaveras Dam, is our system’s largest drinking water reservoir in the local Bay Area. When full it provides more than half of our Bay Area storage capacity for 2.6 million customers. The existing earth fill dam is 87 years old and is located within 1,500 feet of the Calaveras earthquake fault. In 2001 we lowered water levels in the reservoir to less than 40 percent of normal operating capacity in response to seismic concerns.   The Calaveras Dam Replacement Project is the largest project of the $4.6 billion Water System Improvement Program (WSIP) to repair, replace, and seismically upgrade key components of the Hetch Hetchy Regional Water System.
Work Completed to date
Construction began in August 2011 to build a new earth and rock fill dam adjacent to the existing dam. Since then, the Contractor has moved nearly two million cubic yards of earth and rock materials to make room for the new dam. Crews have prepared disposal sites, constructed a soldier pile tie-back wall to stabilize a landslide in the right abutment (the right side of the valley as you face downstream from the dam, away from the reservoir), and began injecting cement grout deep into the joints in the rock of the dam’s foundation. The team has excavated to the new dam’s foundation and has started to build the new dam. In addition, we have begun construction of connecting outlets from the reservoir, and successfully completed the first 2-month closure of Calaveras Road in spring 2012.  However, there is still a great deal of work that lies ahead, with the project only 26% percent complete as of November 2012.

For more project info, contact us at our 24 hour answer line at (866) 973-1476 or email mle@sfwater.org 

Monday, November 12, 2012

Calaveras Road: Increased Truck Traffic 11/13 thru 11/16

The Calaveras Dam Replacement Project will be expecting heavy truck traffic from November 13th through November 16th on Calaveras Road just south of Interstate 680 to the project site approximately 4 miles past Geary Road.  Dates subject to change dependent on weather conditions.
  • Calaveras Road remains open to the public
  • Haul trucks are expected from 7:00 a.m. to 5:00 p.m.
  • Please drive safely on the narrow portions of Calaveras Road and please share the road
  • Speed limit is 25 mph in construction zones
For more information:
24 hour-Answer Line 866-973-1476
Email us:
Follow us online at: www.sfwater.org/sunolvalley

Friday, May 11, 2012

Calaveras Dam Project Team Welcomes AMGEN

Road Closure Update

Calaveras Road will be OPEN to the public to accommodate the AMGEN Tour from 6:00 a.m. to 6:00 p.m. on Tuesday, May 15, 2012 between Geary Road to the Alameda/Santa Clara County boundary. The AMGEN Tour of California will begin Stage 3 of their race in San Jose and riders will cycle through Calaveras Road and Highway 84. Please expect an increase in traffic during this event.

After May 15th, the road closure will return to its regular schedule of April 9, 2012 to June 8, 2012, during which Calaveras Road will be CLOSED to vehicle, pedestrian, and bicycle traffic between Geary Road to the Alameda / Santa Clara County boundary on weekdays ONLY, open on weekends.

For more info on the AMGEN Tour of California visit: www.amgentourofcalifornia.com

For more project info, contact us at our 24 hour answer line at (866) 973-1476 or email mle@sfwater.org

Wednesday, April 4, 2012

Calaveras Road Closure: April 9, 2012 thru June 8, 2012

Calaveras Road, in unincorporated county areas, will be CLOSED to vehicle, pedestrian, and bicycle traffic between Geary Road to the Alameda / Santa Clara County boundary beginning April 9, 2012 through June 8, 2012, Monday through Friday.

Large trucks will be hauling materials on Calaveras Road, as part of the Calaveras Dam Replacement Project. It is not safe for these large vehicles to share these narrow portions of the road with private vehicles and bicycles.

Calaveras Road will be open on weekends, 6:00 a.m. Saturdays through midnight on Sundays. The road will be swept prior to each opening. Emergency vehicles would have access to the road at all times. Access to the Sunol Ohlone Wilderness will remain open from the north at all times. From both the north and south on weekends. Access to Ed Levin County Park and will remain open at all times.

For More Information: 24 hour-Answer Line 866-973-1476 or email: mle@sfwater.org