Friday, June 20, 2014
The WSIP Turns 10!
This year the Water System Improvement Program (WSIP) turns 10! One of the largest infrastructure projects in the nation, the WSIP is repairing, replacing and upgrading our aging water infrastructure to ensure we can deliver water to customers following an earthquake. We’ve gotten a little nostalgic about how far we’ve come in the last 10 years, and we would like to share this video with you.
Now 80 percent complete, the WSIP has already provided increased reliability to the water supply for customers as a result of the completion of some of the program’s major projects. The program has created over 6 million construction craft hours to date, employing more than 11,000 workers since 2007. Nearly half of those workers live in our four-county service area.
An Ode to the Calaveras Spillways, old and new
Workers repair original Calaveras Dam spillway in 1939
What
is a spillway?
A
spillway is an important safety feature on a dam that impounds water behind it
to prevent the dam from overtopping and suffering damage during a flood. The
spillway is often an open chute or channel that allows water when it reaches a
high level in the reservoir to safely bypass the dam and flow downstream
without causing any damage to the dam.History of the Calaveras Dam Spillway
The original spillway on Calaveras Dam was completed in 1925. In 1939, workers had to repair the original spillway after damage was caused by a flood occurred in the Winter of 1937-1938.
Spillway Work Today
Back in March work began on the new spillway. We have made much progress since then to construct the spillway, which will be 1550 feet long. Approximately 40,000 cubic yards of concrete, equivalent to one football field filled six feet deep, is being used to build the structure. All of the concrete is being supplied by our on-site concrete batch plant.
Because of its crucial function in dam safety, it’s important to make sure that the spillway structure stays intact during an earthquake on the nearby Calaveras Fault. So we are drilling anchors, a solid steel rod, about 25 feet into the rock around the spillway to provide support and prevent damage to the structure during any seismic activity. We are installing 1,825 anchors, that’s a lot of anchors! The spillway is expected to be completed in mid-2015.
View of the left wall of
the new Calaveras Dam spillway. The purple anchor in the foreground will be
encased in the concrete slab (foundation) being formed here. The exposed ends
of the wall anchors will be encased in a block of concrete as part of the spillway
wall.
Aerial view of new spillway taking shape at the left abutment.
Red arrows indicate the top of the spillway.
Red arrows indicate the top of the spillway.
Tuesday, June 10, 2014
Neighbors Catch up on the New Irvington Tunnel
Thank you to all of the community members who
dropped by the New Irvington Tunnel Open House at the Mission Coffee House last
week! It was really great to see you. For those of you
who weren’t able to attend, here are the highlights as shared by the project
team.
- The
New Irvington Tunnel Project is currently 95% complete.
- The
steel liner of the tunnel has been installed. We are welding and grouting
the space between the tunnel lining and the outside of the tunnel to seal
the tunnel off from groundwater intrusion.
- The
3.5 mile New Irvington Tunnel will be brought into service sometime this
fall 2014, allowing us to take the old tunnel out of service for
inspection and possible repairs.
- Overall
project completion is anticipated in fall 2015, soon after we complete
site restoration of all of the above ground work.
- The New Irvington Tunnel runs parallel to the existing tunnel (which was built in 1932) between the Sunol Valley south of Highway I-680 and Fremont, California. It provides a seismically designed connection between Sierra Nevada and Alameda Watershed water supplies and 2.6 million Bay Area customers.
We will be back out with another open house in a
about three months, so we hope you can make the next one.
Neighbors have some
tunnel talk at the New Irvington Tunnel Open House
Thursday, May 29, 2014
New Irvington Tunnel Project Open House on June 3rd
Construction on the New
Irvington Tunnel is nearing completion! We anticipate commissioning the new
tunnel sometime this Fall 2014. The new tunnel will provide a seismically-designed connection between water supplies from the Sierra Nevada Mountains and the Alameda Watershed, providing water to our 2.6 million customers. Work
still lies ahead, with project completion expected in mid-2015.
Join us on June 3, 2014 from 4:30 pm to 6:30 pm at Mission Coffee House (151 Washington Blvd., Fremont CA). The project team will be present to answer any of your questions and discuss what to expect post-construction for our Groundwater Management Plan participants.
View from inside a section of the New Irvington Tunnel
Tuesday, May 27, 2014
Alameda County Residents Contribute to 10 Years of WSIP Success
It seems like only yesterday the San Francisco Public Utilities Commission launched the Water System Improvement Program (WSIP). However, April marked the 10-year anniversary of WSIP, and, perhaps it seems like time has flown by since we’ve been busy at work!! Since the start, 11,000 workers have been employed by the program.
Nearly six million craft hours have been completed on the program to date, which includes 725,000 apprenticeship hours. Plus, San Francisco and service-area residents have worked 50 percent of those craft hours. In fact, Alameda County residents are responsible for the largest percentage of total hours worked on WSIP out of all the participating counties!
Thanks in part to the hard work of Alameda County residents, the WSIP is now 80 percent complete. The WSIP will ensure the Hetch Hetchy Regional Water System, which serves 2.6 million customers in the Bay Area, will be able to withstand a major earthquake or drought and continue to deliver water to customers.
A crew member upgrades the San Antonio Pump Station, a key WSIP project now complete.
Nearly six million craft hours have been completed on the program to date, which includes 725,000 apprenticeship hours. Plus, San Francisco and service-area residents have worked 50 percent of those craft hours. In fact, Alameda County residents are responsible for the largest percentage of total hours worked on WSIP out of all the participating counties!
Thanks in part to the hard work of Alameda County residents, the WSIP is now 80 percent complete. The WSIP will ensure the Hetch Hetchy Regional Water System, which serves 2.6 million customers in the Bay Area, will be able to withstand a major earthquake or drought and continue to deliver water to customers.
A crew member upgrades the San Antonio Pump Station, a key WSIP project now complete.
Thursday, May 8, 2014
Sunol Glen School Students Celebrate Earth Week with Us!
What
do ancient shark teeth, wasps nests, and owl pellets have in common? All were
on display last week at the Sunol Glen School’s Earth Day Science celebration
last week. We were lucky
enough to have been invited to participate, along with other local groups and
leaders. The kids, grades
Kindergarten through eighth grade, learned about the importance of building a
seismically upgraded replacement dam at the Calaveras Reservoir. Our project
Geologist Bradley Erskine showed some fascinating fossils found at the
Calaveras site during construction. The biggest hit with the students by far
was a prehistoric shark tooth possibly from a Megladon, dating at approximately
20 million years old. We had a great time answering questions about how
water gets to your tap and the importance of the Water System Improvement
Program to future generations.
Having met the leaders of tomorrow at Sunol Glen School, we know the future is in good hands! Sunol Glen Schools students proved themselves to be inquisitive and curious scientists at Earth Day on May 2nd.
Having met the leaders of tomorrow at Sunol Glen School, we know the future is in good hands! Sunol Glen Schools students proved themselves to be inquisitive and curious scientists at Earth Day on May 2nd.
Geologist Bradley Erskine and Natural Resources staffer Amy Dawson share fossil finds from Calaveras Dam to the Sunol Glen School students
Sample fossils of prehistoric shark teeth dating over 20 million years old
Friday, April 25, 2014
Critters, Kids and Parents oh my!! All Tested their WSIP Facts at the Sunol Wildflower Festival
Community members and even an enthusiastic furry friend joined the Water System Improvement Program (WSIP) team to learn about water conservation, local wildlife and the Sunol Valley Watershed at the Sunol Wildflower Festival earlier this month. Visitors to our booth tested their knowledge of WSIP facts by spinning the prize wheel to with fun prizes. In case you missed the Festival, here are a couple of the most challenging questions:
· How many gallons of water does the washing machine use? 55 gallons
· Why would we have injected more than 8 million pounds of cement grout into the New Irvington Tunnel during construction? To seal the tunnel heading off from groundwater intrusion
A special thank you to our partners at the East Bay Regional Park District and Alameda Creek Alliance for hosting this wonderful event.
· How many gallons of water does the washing machine use? 55 gallons
· Why would we have injected more than 8 million pounds of cement grout into the New Irvington Tunnel during construction? To seal the tunnel heading off from groundwater intrusion
A special thank you to our partners at the East Bay Regional Park District and Alameda Creek Alliance for hosting this wonderful event.
Subscribe to: