We wanted to
share a spooky tale from the Calaveras Dam Replacement Project. It seems even
state-of-the-art construction projects aren’t without their spooky places.
While moving
the rock and soil to make space for the new replacement Calaveras Dam, workers
uncovered what looked like holes dug into the area surrounding the existing
dam.
The holes are
actually adits excavated by the builders of the first Calaveras Dam.
Technically, an adit is an entrance or tunnel into a mine. Back in the early 1900’s the best way engineers had to explore the rock and soil for a damsite was to excavate adits to look at the underground geology. There are 16 total adits that were uncovered at the site.
Technically, an adit is an entrance or tunnel into a mine. Back in the early 1900’s the best way engineers had to explore the rock and soil for a damsite was to excavate adits to look at the underground geology. There are 16 total adits that were uncovered at the site.
We knew about
the presence of these adits before we started to dig for the new dam foundation.
However, it didn’t ease the creepy feeling workers had when they uncovered
them. And some even claim equipment broke down and didn’t work properly while
they were working around the adits, as if they were haunted.
The adits are
mapped and filled in with concrete or rock to stabilize the ground prior to
constructing the new dam on top, and to seal in any spooks that might be still
be there…just in time for Halloween!
Friday, October 21, 2016
Photo Friday in Sunol Valley
This week we wanted to share a snapshot of construction underway at the
Fish Passage Facilities in Sunol Valley. The photo below shows the new intake structure and conveyance tunnels under construction upstream of the Alameda Creek Diversion Dam. The Fish Passage Facilities Project is located on SFPUC property adjacent to the Sunol Regional Wilderness. Completion of the project will support the restoration of steelhead trout to the Alameda Creek watershed. Happy Friday!
Fish Passage Facilities in Sunol Valley. The photo below shows the new intake structure and conveyance tunnels under construction upstream of the Alameda Creek Diversion Dam. The Fish Passage Facilities Project is located on SFPUC property adjacent to the Sunol Regional Wilderness. Completion of the project will support the restoration of steelhead trout to the Alameda Creek watershed. Happy Friday!
Friday, October 14, 2016
Remembering Loma Prieta – And Preparing for the Next Big One
Monday, October 17th is the 27th anniversary of
the Loma Prieta Earthquake. The 6.9 magnitude quake shook the earth for 15
seconds, took the lives of 67 people and injured almost 3,000 more. There was
an estimated $6 billion in property losses. We here at the San Francisco Public
Utilities Commission have been preparing for the next big quake ever since.
As the owner and operator of the Hetch Hetchy Regional Water System that
serves water to 2.6 million people in four Bay Area counties, we have worked
for more than 10 years to repair, replace, and seismically upgrade vulnerable
portions of this system as part of the $4.8 billion Water System Improvement
Program (WSIP). The program itself is more than 90% complete. Our water system
is safer and more reliable today than it was 10 years ago, let alone 27 years
ago. Our promise is that we can deliver minimum demand to our customers within
24 hours after a major earthquake. We can make good on that promise because of
WSIP.
Here’s just a few reasons why:
* The Bay Tunnel is a seismic lifeline carrying water under San
Francisco Bay. It was brought into service on time and under budget in October
2014.
* The New Irvington Tunnel carries water between our East Bay and Hetch
Hetchy supplies and our Bay Area Customers. Located between the Calaveras and
Hayward Earthquake faults, this seismically designed tunnel allows us to take
the existing 88 year-old tunnel out of service for maintenance.
* A new Bay Division Pipeline #5 connects to both of these new tunnels
in the East Bay and on the Peninsula to provide greater delivery reliability to
our customers. It replaces two pipes that were constructed in 1926 and 1935.
Wait, that’s not all!
We upgraded our Sunol Valley
Water Treatment Plant, which treats water from San Antonio and Calaveras
Reservoirs. It can now treat enough water to support our entire service
territory on its own (160 million gallons of water per day) for up to 60
days after a major earthquake.
Water treatment trains at our
newly upgraded Sunol Valley Water Treatment Plant
Two
major transmission lines sit on major traces of the Hayward Fault in Fremont.
We used cutting-edge technology on our Bay Division Pipelines 3 and 4 to allow
one of them to absorb up to 6.5 feet of horizontal displacement and 9 feet of
compression while still remaining in service.
A slip joint at the Seismic
Upgrades to the Bay Division Pipelines 3 and 4 at the Hayward Fault Crossing
allows the pipe to absorb up to 9 feet of compression during an earthquake.
This work is never done. We will continue to replace and
upgrade our system pipelines, pump stations, and treatment plants even after
the WSIP is complete. We’ll worry about your water so you won’t have to.
Thursday, September 29, 2016
Mountain Lions at Calaveras Dam
Just this
week at the Calaveras Dam Replacement Project, crews were able to install a
special feature to the new Intake Tower roof.
The new intake tower is part of the outlet works that releases water from
the reservoir. The special features are roof drain scuppers made of cast bronze
in the shape of a mountain lion head designed by artist Manuel Palos and architect Andrew Maloney.
Why a Mountain Lion?
The lion head “grotesque” & “gargoyle” ornament has decorated
buildings for thousands of years. In Greek and Roman classical architecture,
the lion was a symbol of the fallen hero, guardian of gates, temples, and
public buildings. The rain
water from the roof is collected in the drain and exits the mouth of the
mountain lion.
Mountain lions are native to the Alameda Creek Watershed. Some construction
workers have seen them on site and we even captured footage on our trail
camera:
Friday, September 23, 2016
Sunol Glen School Walk-a-Thon
Well, now it is officially fall. Sure, the Autumnal Equinox
was yesterday, but today, more importantly, is Sunol Glen School’s Annual Walk-a-thon!
It is the Sunol Glen Community Club’s largest fundraiser.
We at the SFPUC are pleased and proud to be out there again
this year to provide drinking water and moral support to the amazing student
participants.
How can you show your support, you ask?
Visit www.sunolglencc.com to learn more!
Wendie and Carlos (at right) and Maria and Dylan (below) show their true blue Eagles Spirit!
Thursday, September 15, 2016
Work on the Drainage System for Calaveras Dam
This week our
crews started installation of two drainage pipes which are 100 feet long and 18
inches in diameter. Why are these important?
A major component
of earthen fill dams is to control water seepage. Seepage occurs with the continuous
movement of water around and through the dam. Earthen fill dams are designed
with filter drain materials. The new Calaveras Dam will have filter drains composed
of sands and gravel materials, which are being imported to the project site. The filter drains collect the seepage. The water
goes into the drainage pipes shown below and flows to a weir building, where it
is measured continuously to ensure water is passing safely. Eventually the
water will flow downstream to the nearby creeks. The completion of the
Calaveras Dam is critical to restore the Calaveras Reservoir to its historic storage
capacity of 31 billion gallons of water storage for the Hetch Hetchy Regional
Water System.
Perforated
Pipes being installed adjacent to the inspection well for the new Calaveras Dam
Installation of drainage
pipes below the new spillway for the Calaveras Dam Replacement Project
Subscribe to:
Posts (Atom)