Tunneling began just over a month ago at Irvington Portal off of Mission Blvd. and work is rapidly progressing. On Monday of last week, workers continued from the previous week at a distance of 82 feet. With lots of hard work and the help of the roadheader grinding away, they ended on Friday at 146 feet. That’s an additional 64 feet in just one week!

Just off the 680 freeway lies the Vargas Shaft, where work began in early 2011. Tunneling has stopped for the moment as workers are busy drilling drain holes to discharge excess water from the tunnel, which will allow for easier tunneling. Tunneling will hopefully resume this week after which workers will be headed westward!