We are getting started on construction to improve the water distribution system and construct approximately 26 fire hydrants in the Town of Sunol. 

Please join us for a project groundbreaking on Friday, July 11, at 10:30 a.m. at the parking lot (intersection of Main Street, Kilkare Road, and Foothill Road) in Sunol, California.
We will enjoy light refreshments at the park afterwards.

Where is construction right now?
During the Weeks of July 7—July 21, 2014

Pipeline installation will occur at:
  • Sunol Glen School
  • Main Street up to the Railroad Crossing
  • Bond Street
In August, we plan:
  • Pipeline Installation on East Foothill Road to  the Kilkare Road intersection
  • Jack and Bore crossing underneath Alameda County Railway at the intersection of Main Street, Kilkare Road, and Foothill Road.
o   We will cross under the railroads using a jack and bore method. The contractor will dig two large pits on each side of the crossing, insert pipeline casing into the pits and move the pipe beneath the railroad crossings. Each jack and bore crossing will take approximately 30 days.

What to Expect during Construction:
  • One-lane traffic through construction zones during work hours. This will cause some delays, so please plan ahead.
  • Possible Work Hours: 7:00 a.m. to 5:00 p.m.
  • Weekend work might be necessary, but we will provide advanced notice.
  • Night work will be necessary during pipeline/tank shutdowns. We will minimize noise.  Some residents will have nighttime water outages with advance notice.
  • Access to private driveways and around streets will be available at all times.